Question 140
At a logistics and warehousing campus, the access-network team reports that a VSX active-gateway deployment sends inconsistent ARP replies from its peers. Select TWO complementary choices: the targeted response and an acceptance test that verifies it.
Explanation
Correct Answers
The selected action is Inspect ARP records and first-hop connectivity after peer switchover. Its matching outcome check is to inspect ARP records and first-hop connectivity after peer switchover.
The selected action is Align the virtual gateway MAC/IP configuration and VLAN context on both peers. Its matching outcome check is to inspect ARP records and first-hop connectivity after peer switchover.
Incorrect Answers
The proposed alternative—test a controlled peer failure and inspect LACP and forwarding—does not address the current failure. Instead, align the virtual gateway MAC/IP configuration and VLAN context on both peers.
The proposed alternative—assign and verify primary and secondary spanning-tree root priorities for intended VLANs—does not address the current failure. Instead, align the virtual gateway MAC/IP configuration and VLAN context on both peers.
The proposed alternative—monitor appropriate upstream health and couple it to gateway failover policy—does not address the current failure. Instead, align the virtual gateway MAC/IP configuration and VLAN context on both peers.
Question 141
At a municipal public library system, the operations team reports that a distribution switch failure causes slow, unexpected layer-2 reconvergence across campus. Which configuration or operating decision most directly addresses the issue?
Explanation
Correct Answer
Assign and verify primary and secondary spanning-tree root priorities for intended VLANs. Deterministic root placement makes backup topology behavior predictable. Confirm the result using this test: Inspect root bridge identity before and after a planned failure.
Incorrect Answers
The proposed alternative—compare tracked objects, priorities and preemption policy on the redundant pair—does not address the current failure. Instead, assign and verify primary and secondary spanning-tree root priorities for intended VLANs.
The proposed alternative—inspect VSF link topology, member IDs and compatible software before recovery—does not address the current failure. Instead, assign and verify primary and secondary spanning-tree root priorities for intended VLANs.
The proposed alternative—configure a resilient virtual gateway mechanism with monitored upstream reachability—does not address the current failure. Instead, assign and verify primary and secondary spanning-tree root priorities for intended VLANs.
Question 142
At a municipal public library system, the operations team reports that a distribution switch failure causes slow, unexpected layer-2 reconvergence across campus. A design review identifies an unsupported shortcut. Which assumption should the team reject for this particular problem?
Explanation
Correct Answer
The shortcut at issue is to give every access port bridge the same root priority and rely on luck. The corrective choice is: Assign and verify primary and secondary spanning-tree root priorities for intended VLANs.
Incorrect Answers
The shortcut to set the same physical IP manually on two independent gateways is not the error in this case. The actual risk comes from give every access port bridge the same root priority and rely on luck.
The shortcut to configure conflicting gateway MAC values for the same shared VLAN is not the error in this case. The actual risk comes from give every access port bridge the same root priority and rely on luck.
The shortcut to connect both uplinks as independent unprotected access ports is not the error in this case. The actual risk comes from give every access port bridge the same root priority and rely on luck.
Question 143
At a municipal public library system, the operations team reports that a distribution switch failure causes slow, unexpected layer-2 reconvergence across campus. Which technical reasoning most specifically justifies the recommended solution?
Explanation
Correct Answer
Deterministic root placement makes backup topology behavior predictable. This is the technical reason behind the proposed approach: “Assign and verify primary and secondary spanning-tree root priorities for intended VLANs”. The result should be checked by “Inspect root bridge identity before and after a planned failure”.
Incorrect Answers
The proposed alternative—parallel Ethernet paths require a loop-safe control-plane mechanism—does not address the current failure. Instead, assign and verify primary and secondary spanning-tree root priorities for intended VLANs.
The proposed alternative—device uptime alone cannot prove the forwarding service is available—does not address the current failure. Instead, assign and verify primary and secondary spanning-tree root priorities for intended VLANs.
The proposed alternative—a separate keepalive path reduces ambiguity during an inter-switch failure—does not address the current failure. Instead, assign and verify primary and secondary spanning-tree root priorities for intended VLANs.
Question 144
At a municipal public library system, the operations team reports that a distribution switch failure causes slow, unexpected layer-2 reconvergence across campus. Which test would most directly show that the requested outcome was achieved?
Explanation
Correct Answer
The outcome check is to inspect root bridge identity before and after a planned failure. It measures whether the stated requirement was met.
Incorrect Answers
The suggested check—inspect ISL state and VSX consistency diagnostics on both peers—does not test the required result. Instead, inspect root bridge identity before and after a planned failure.
The suggested check—validate synchronization and shared forwarding in a lab failover—does not test the required result. Instead, inspect root bridge identity before and after a planned failure.
The suggested check—check keepalive ping, VSX state and link-failure behavior—does not test the required result. Instead, inspect root bridge identity before and after a planned failure.
Question 145
At a municipal public library system, the operations team reports that a distribution switch failure causes slow, unexpected layer-2 reconvergence across campus. Select TWO complementary choices: the targeted response and an acceptance test that verifies it.
Explanation
Correct Answers
The selected action is Assign and verify primary and secondary spanning-tree root priorities for intended VLANs. Its matching outcome check is to inspect root bridge identity before and after a planned failure.
The selected action is Inspect root bridge identity before and after a planned failure. Its matching outcome check is to inspect root bridge identity before and after a planned failure.
Incorrect Answers
The proposed alternative—check the supported state synchronization and maintenance sequence for that platform—does not address the current failure. Instead, assign and verify primary and secondary spanning-tree root priorities for intended VLANs.
The proposed alternative—verify the VSX ISL and its correct LAG members before altering downstream VLANs—does not address the current failure. Instead, assign and verify primary and secondary spanning-tree root priorities for intended VLANs.
The proposed alternative—test a controlled peer failure and inspect LACP and forwarding—does not address the current failure. Instead, assign and verify primary and secondary spanning-tree root priorities for intended VLANs.
Question 146
At a large school district, the IT team reports that an access closet has two redundant uplinks but forms a loop when both are connected. Which configuration or operating decision most directly addresses the issue?
Explanation
Correct Answer
Use the intended LAG or spanning-tree design instead of unmanaged parallel links. Parallel Ethernet paths require a loop-safe control-plane mechanism. Confirm the result using this test: Test failure of one uplink while monitoring loop and forwarding state.
Incorrect Answers
The proposed alternative—verify member identity, software compatibility and current approved group configuration—does not address the current failure. Instead, use the intended LAG or spanning-tree design instead of unmanaged parallel links.
The proposed alternative—assign and verify primary and secondary spanning-tree root priorities for intended VLANs—does not address the current failure. Instead, use the intended LAG or spanning-tree design instead of unmanaged parallel links.
The proposed alternative—configure the supported multichassis LAG arrangement with synchronized member settings—does not address the current failure. Instead, use the intended LAG or spanning-tree design instead of unmanaged parallel links.
Question 147
At a large school district, the IT team reports that an access closet has two redundant uplinks but forms a loop when both are connected. A design review identifies an unsupported shortcut. Which assumption should the team reject for this particular problem?
Explanation
Correct Answer
The shortcut at issue is to connect both uplinks as independent unprotected access ports. The corrective choice is: Use the intended LAG or spanning-tree design instead of unmanaged parallel links.
Incorrect Answers
The shortcut to assume a powered AP means client data tunnels always have a viable gateway is not the error in this case. The actual risk comes from connect both uplinks as independent unprotected access ports.
The shortcut to trigger failover only after the entire gateway loses electrical power is not the error in this case. The actual risk comes from connect both uplinks as independent unprotected access ports.
The shortcut to restore any old backup without comparing stack or peer identifiers is not the error in this case. The actual risk comes from connect both uplinks as independent unprotected access ports.
Question 148
At a large school district, the IT team reports that an access closet has two redundant uplinks but forms a loop when both are connected. Which technical reasoning most specifically justifies the recommended solution?
Explanation
Correct Answer
Parallel Ethernet paths require a loop-safe control-plane mechanism. This is the technical reason behind the proposed approach: “Use the intended LAG or spanning-tree design instead of unmanaged parallel links”. The result should be checked by “Test failure of one uplink while monitoring loop and forwarding state”.
Incorrect Answers
The proposed alternative—redundant hardware does not guarantee every session survives a takeover—does not address the current failure. Instead, use the intended LAG or spanning-tree design instead of unmanaged parallel links.
The proposed alternative—a separate keepalive path reduces ambiguity during an inter-switch failure—does not address the current failure. Instead, use the intended LAG or spanning-tree design instead of unmanaged parallel links.
The proposed alternative—wireless control connectivity and user traffic forwarding can fail separately—does not address the current failure. Instead, use the intended LAG or spanning-tree design instead of unmanaged parallel links.
Question 149
At a large school district, the IT team reports that an access closet has two redundant uplinks but forms a loop when both are connected. Which test would most directly show that the requested outcome was achieved?
Explanation
Correct Answer
The outcome check is to test failure of one uplink while monitoring loop and forwarding state. It measures whether the stated requirement was met.
Incorrect Answers
The suggested check—inspect ARP records and first-hop connectivity after peer switchover—does not test the required result. Instead, test failure of one uplink while monitoring loop and forwarding state.
The suggested check—check keepalive ping, VSX state and link-failure behavior—does not test the required result. Instead, test failure of one uplink while monitoring loop and forwarding state.
The suggested check—examine VSF topology and restore the missing member safely—does not test the required result. Instead, test failure of one uplink while monitoring loop and forwarding state.
Question 150
At a large school district, the IT team reports that an access closet has two redundant uplinks but forms a loop when both are connected. Select TWO complementary choices: the targeted response and an acceptance test that verifies it.
Explanation
Correct Answers
The selected action is Use the intended LAG or spanning-tree design instead of unmanaged parallel links. Its matching outcome check is to test failure of one uplink while monitoring loop and forwarding state.
The selected action is Test failure of one uplink while monitoring loop and forwarding state. Its matching outcome check is to test failure of one uplink while monitoring loop and forwarding state.
Incorrect Answers
The proposed alternative—measure default-gateway reachability during a switch failover—does not address the current failure. Instead, use the intended LAG or spanning-tree design instead of unmanaged parallel links.
The proposed alternative—compare tracked objects, priorities and preemption policy on the redundant pair—does not address the current failure. Instead, use the intended LAG or spanning-tree design instead of unmanaged parallel links.
The proposed alternative—inspect VSF link topology, member IDs and compatible software before recovery—does not address the current failure. Instead, use the intended LAG or spanning-tree design instead of unmanaged parallel links.
HPE Network Campus Access Professional (HPE7-A01) Practice Tests
- HP HPE7-A01 Practice Test 13 - 10 Questions (Last Reviewed 06-Nov-2026)
- HP HPE7-A01 Practice Test 14 - 10 Questions (Last Reviewed 05-Nov-2026)
- HP HPE7-A01 Practice Test 15 - 10 Questions (Last Reviewed 04-Nov-2026)
- HP HPE7-A01 Practice Test 16 - 10 Questions (Last Reviewed 03-Nov-2026)
- HP HPE7-A01 Practice Test 17 - 10 Questions (Last Reviewed 02-Nov-2026)