Question 70
A predictive project delivery setting is used, with formal milestones and baseline control. The project situation is: A vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. A readiness review shows the current management approach is ineffective. Which corrective action BEST resolves the exact gap?
Explanation
Correct Answer
To correct the failure where a vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement, examine the contract and accepted scope, facilitate a fact-based decision, and document the resulting change or defect disposition. The team can validate the repair by arranging to trace the disputed feature through signed scope, acceptance criteria and documented decision.
Incorrect Answers
Charge the customer automatically for every disputed item without reviewing acceptance evidence retains the error identified in the incident; it is not a repair. The appropriate corrective action is to examine the contract and accepted scope, facilitate a fact-based decision, and document the resulting change or defect disposition.
Changing the system to separate contractual facts from interpersonal assumptions and mediate a joint interface baseline with accountable owners would not reverse the specified failure: a vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. The corrective change is to examine the contract and accepted scope, facilitate a fact-based decision, and document the resulting change or defect disposition.
Changing the system to address the root constraints in a facilitated discussion and agree documented decision criteria and ownership would not reverse the specified failure: a vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. The corrective change is to examine the contract and accepted scope, facilitate a fact-based decision, and document the resulting change or defect disposition.
Question 71
A predictive project delivery setting is used, with formal milestones and baseline control. The project situation is: A vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. Which pre-release planning or approval gate would BEST avoid this problem and preserve necessary governance?
Explanation
Correct Answer
Approval gate: Examine the contract and accepted scope, facilitate a fact-based decision, and document the resulting change or defect disposition. The gate requires this specific check again after later changes, rather than relying on a one-time approval.
Incorrect Answers
Approval gate: Address the root constraints in a facilitated discussion and agree documented decision criteria and ownership does not make future changes demonstrate the required result for the reported case: a vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. The relevant gate is to approval gate: Examine the contract and accepted scope, facilitate a fact-based decision, and document the resulting change or defect disposition.
Approval gate: Separate contractual facts from interpersonal assumptions and mediate a joint interface baseline with accountable owners does not make future changes demonstrate the required result for the reported case: a vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. The relevant gate is to approval gate: Examine the contract and accepted scope, facilitate a fact-based decision, and document the resulting change or defect disposition.
Approval gate: Charge the customer automatically for every disputed item without reviewing acceptance evidence does not make future changes demonstrate the required result for the reported case: a vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. The relevant gate is to approval gate: Examine the contract and accepted scope, facilitate a fact-based decision, and document the resulting change or defect disposition.
Question 72
A predictive project delivery setting is used, with formal milestones and baseline control. The project situation is: A vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. Select TWO complementary records: the appropriate management decision and the observed acceptance result that demonstrates it was effective. Which TWO are required?
Explanation
Correct Answers
This is the required control or corrective action: examine the contract and accepted scope, facilitate a fact-based decision, and document the resulting change or defect disposition. It complements the observed test to trace the disputed feature through signed scope, acceptance criteria and documented decision.
Trace the disputed feature through signed scope, acceptance criteria and documented decision. That observation tests whether the response works for the actual condition: a vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement.
Incorrect Answers
The proposed evidence—check signed interface requirements and meeting decisions for clear commitments and dates—checks a different result rather than the one established by this case: a vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. The aligned check is to trace the disputed feature through signed scope, acceptance criteria and documented decision.
The proposed evidence—review whether the agreed cutover criteria unblock estimates and preserve unresolved trade-offs—checks a different result rather than the one established by this case: a vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. The aligned check is to trace the disputed feature through signed scope, acceptance criteria and documented decision.
The proposed evidence—review the agreed priority rules and a subsequent contested sprint decision—checks a different result rather than the one established by this case: a vendor's project manager and the customer disagree about whether a late feature is a defect or an enhancement. The aligned check is to trace the disputed feature through signed scope, acceptance criteria and documented decision.
Question 73
An adaptive/agile project delivery setting is used, with iterative feedback and product prioritization. The project situation is: A new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. What is the BEST next project management decision to achieve the intended result while retaining accountable stakeholder ownership?
Explanation
Correct Answer
Because a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency, set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes. A suitable check is to observe decision cycle time and team-owned commitments in a controlled iteration.
Incorrect Answers
Require manager approval for all routine technical choices to signal leadership control is precisely the unsafe assumption that the design needs to avoid when a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The proposed control is to set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes.
Delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency would not satisfy the actual requirement: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The implementation must instead set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes.
Establish transparent accountable roles and integrated working agreements across suppliers and staff would not satisfy the actual requirement: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The implementation must instead set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes.
Question 74
An adaptive/agile project delivery setting is used, with iterative feedback and product prioritization. The project situation is: A new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. Which mistaken management shortcut MOST directly explains the risk or failed outcome in this situation?
Explanation
Correct Answer
The flawed assumption is to require manager approval for all routine technical choices to signal leadership control; that decision does not account for the condition that a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The corresponding control is to set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes.
Incorrect Answers
Add more status meetings without assigning a test owner is not the particular mistake underlying the evidence that a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The relevant flawed assumption is to require manager approval for all routine technical choices to signal leadership control.
Treat the expert's speed as sufficient justification for excluding the rest of the team is not the particular mistake underlying the evidence that a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The relevant flawed assumption is to require manager approval for all routine technical choices to signal leadership control.
Publicly compare the analyst to less productive colleagues in a reprimand is not the particular mistake underlying the evidence that a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The relevant flawed assumption is to require manager approval for all routine technical choices to signal leadership control.
Question 75
An adaptive/agile project delivery setting is used, with iterative feedback and product prioritization. The project situation is: A new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. A readiness review shows the current management approach is ineffective. Which corrective action BEST resolves the exact gap?
Explanation
Correct Answer
To correct the failure where a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency, set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes. The team can validate the repair by arranging to observe decision cycle time and team-owned commitments in a controlled iteration.
Incorrect Answers
Changing the system to delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency would not reverse the specified failure: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The corrective change is to set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes.
Changing the system to establish transparent accountable roles and integrated working agreements across suppliers and staff would not reverse the specified failure: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The corrective change is to set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes.
Require manager approval for all routine technical choices to signal leadership control retains the error identified in the incident; it is not a repair. The appropriate corrective action is to set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes.
Question 76
An adaptive/agile project delivery setting is used, with iterative feedback and product prioritization. The project situation is: A new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. Which pre-release planning or approval gate would BEST avoid this problem and preserve necessary governance?
Explanation
Correct Answer
Approval gate: Set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes. The gate requires this specific check again after later changes, rather than relying on a one-time approval.
Incorrect Answers
Approval gate: Require manager approval for all routine technical choices to signal leadership control does not make future changes demonstrate the required result for the reported case: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The relevant gate is to approval gate: Set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes.
Approval gate: Establish transparent accountable roles and integrated working agreements across suppliers and staff does not make future changes demonstrate the required result for the reported case: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The relevant gate is to approval gate: Set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes.
Approval gate: Delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency does not make future changes demonstrate the required result for the reported case: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The relevant gate is to approval gate: Set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes.
Question 77
An adaptive/agile project delivery setting is used, with iterative feedback and product prioritization. The project situation is: A new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. Select TWO complementary records: the appropriate management decision and the observed acceptance result that demonstrates it was effective. Which TWO are required?
Explanation
Correct Answers
Observe decision cycle time and team-owned commitments in a controlled iteration. That observation tests whether the response works for the actual condition: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency.
This is the required control or corrective action: set decision boundaries and empower the team to self-organize while maintaining clear accountability for outcomes. It complements the observed test to observe decision cycle time and team-owned commitments in a controlled iteration.
Incorrect Answers
The proposed evidence—verify an integration test has a named owner, evidence and escalation path—checks a different result rather than the one established by this case: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The aligned check is to observe decision cycle time and team-owned commitments in a controlled iteration.
The proposed evidence—inspect adjusted workload and subsequent performance and team feedback—checks a different result rather than the one established by this case: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The aligned check is to observe decision cycle time and team-owned commitments in a controlled iteration.
The proposed evidence—sample decisions, peer-review participation and demonstrated backup capability—checks a different result rather than the one established by this case: a new agile delivery team waits for the project manager to approve each small task, delaying feedback and creating dependency. The aligned check is to observe decision cycle time and team-owned commitments in a controlled iteration.
Question 78
A predictive project delivery setting is used, with formal milestones and baseline control. The project situation is: An experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. What is the BEST next project management decision to achieve the intended result while retaining accountable stakeholder ownership?
Explanation
Correct Answer
Because an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn, delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency. A suitable check is to sample decisions, peer-review participation and demonstrated backup capability.
Incorrect Answers
Treat the expert's speed as sufficient justification for excluding the rest of the team is precisely the unsafe assumption that the design needs to avoid when an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. The proposed control is to delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency.
Establish transparent accountable roles and integrated working agreements across suppliers and staff would not satisfy the actual requirement: an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. The implementation must instead delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency.
Discuss workload and motivation privately, rebalance assignments, and provide constructive recognition consistent with team needs would not satisfy the actual requirement: an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. The implementation must instead delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency.
Question 79
A predictive project delivery setting is used, with formal milestones and baseline control. The project situation is: An experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. Which mistaken management shortcut MOST directly explains the risk or failed outcome in this situation?
Explanation
Correct Answer
The flawed assumption is to treat the expert's speed as sufficient justification for excluding the rest of the team; that decision does not account for the condition that an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. The corresponding control is to delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency.
Incorrect Answers
Add more status meetings without assigning a test owner is not the particular mistake underlying the evidence that an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. The relevant flawed assumption is to treat the expert's speed as sufficient justification for excluding the rest of the team.
Replace participatory design sessions with one-way instructions for everyone is not the particular mistake underlying the evidence that an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. The relevant flawed assumption is to treat the expert's speed as sufficient justification for excluding the rest of the team.
Publicly compare the analyst to less productive colleagues in a reprimand is not the particular mistake underlying the evidence that an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. The relevant flawed assumption is to treat the expert's speed as sufficient justification for excluding the rest of the team.
Question 80
A predictive project delivery setting is used, with formal milestones and baseline control. The project situation is: An experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. A readiness review shows the current management approach is ineffective. Which corrective action BEST resolves the exact gap?
Explanation
Correct Answer
To correct the failure where an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn, delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency. The team can validate the repair by arranging to sample decisions, peer-review participation and demonstrated backup capability.
Incorrect Answers
Treat the expert's speed as sufficient justification for excluding the rest of the team retains the error identified in the incident; it is not a repair. The appropriate corrective action is to delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency.
Changing the system to discuss workload and motivation privately, rebalance assignments, and provide constructive recognition consistent with team needs would not reverse the specified failure: an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. The corrective change is to delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency.
Changing the system to establish transparent accountable roles and integrated working agreements across suppliers and staff would not reverse the specified failure: an experienced specialist is taking every critical design decision while newer colleagues have no chance to learn. The corrective change is to delegate meaningful decisions with coaching and knowledge-sharing guardrails to reduce single-person dependency.
Project Management Professional (PMBOK 8) (PMP) Practice Tests
- PMI PMP Practice Test 6 - 10 Questions (Last Reviewed 13-Nov-2026)
- PMI PMP Practice Test 7 - 10 Questions (Last Reviewed 12-Nov-2026)
- PMI PMP Practice Test 8 - 10 Questions (Last Reviewed 11-Nov-2026)
- PMI PMP Practice Test 9 - 10 Questions (Last Reviewed 10-Nov-2026)
- PMI PMP Practice Test 10 - 10 Questions (Last Reviewed 09-Nov-2026)